PUBLIC PATHS IMPROVEMENT PROGRAMME PAROW Home Page

Cornwall County Council is now well over a year into its £2.01M programme of improvements (PPIP) to our bridleways and footpaths .

All footpaths and bridleways have been allocated a priority status of "Gold", "Silver" or "Bronze". Over 50% of paths are Gold. Only Gold paths are being renovated under the PPIP programme. More information on the County Council web Site http://www.cornwall.gov.uk/index.cfm?articleid=15663

The work is scheduled on a parish by parish basis. For the latest schedule on when parishes are being worked on see CC Parish Timetable

The programme has fallen behind the Original Schedule However, despite this, much good work has been achieved in many parishes with fantastic renovations achieved on many footpaths and bridleways..

 

Penwith Parishes (October 2007

Schedule


Majority of works completed
parishes Marazion, The St Michael's Way, Penzance, Perranuthnoe, Paul,
St Buryan

In Progress Ludgvan, St Levan
Oct-Dec 2007 Sennen,
St Just in Penwith, Morvah, Zennor
Jan-Mar 2008
Towednack, St Ives
Apr-Jun 2008
Hayle, Gwinear-Gwithian

Jul-Sept 2008 St Erth, St Hilary
Oct-Nov 2008
Madron, Sancreed